CHANTIER AU 16 AVRIL 2024

Zone 1 EOLIA : avancement global = 5% – Terrassement = 80% • Maçonnerie = 0% – Gros oeuvre = 5% • Second oeuvre = 0% Zone 2 SOLIS : avancement global = 10% – Terrassement = 95% • Maçonnerie = 0%– Gros oeuvre = 10% • Second oeuvre = 5% Zone 3 OASIS : …

CHANTIER AU 16 AVRIL 2024 Lire la suite »