CHANTIER AU 01 JUILLET 2024
Zone 1 EOLIA : avancement global = 10% – Terrassement = 80% • Gros oeuvre = 10% – Maçonnerie = 0% • Lots techniques = 2% – Corps d’état secondaire = 0% Zone 2 SOLIS : avancement global = 15% – Terrassement = 100% • Gros oeuvre = 15% – Maçonnerie = 1% • …