CHANTIER AU 01 JUILLET 2024

Zone 1 EOLIA : avancement global = 10%

– Terrassement = 80% • Gros oeuvre = 10%

– Maçonnerie = 0% • Lots techniques = 2%

– Corps d’état secondaire = 0%

 

Zone 2 SOLIS : avancement global = 15%

– Terrassement = 100% • Gros oeuvre = 15%

– Maçonnerie = 1% • Lots techniques = 2%

– Corps d’état secondaire = 2%

 

Zone 3 OASIS : avancement global = 55%

– Gros oeuvre = 100% • Finitions = 95%

– Maçonnerie = 100% • Lots techniques = 40%

– Corps d’état secondaire = 40%

 

Zone 4 LUMIA : avancement global = 40%

– Gros oeuvre = 95% • Finitions = 35%

– Maçonnerie = 40% • Lots techniques = 10%

– Corps d’état secondaire = 15%

Nos articles

CHANTIER AU 16 AVRIL 2024

Zone 1 EOLIA : avancement global = 5% – Terrassement = 80% • Maçonnerie = 0% – Gros oeuvre = 5% • Second oeuvre =

CHANTIER AU 02 FEV 2024

Zone 3 OASIS : avancement global = 40% – Gros œuvre = 99,97% – Maçonnerie = 99,00% – Corps d’état secondaire = 12% Zone 4

plan 1

CHANTIER AU 02 NOVEMBRE 2023

Zone OASIS : Avancement global = 55,22% – Maçonnerie = 96,39% – Gros œuvre = 99,74 % – Corps d’état secondaire = 40,24%. Zone LUMIA