CHANTIER AU 16 AVRIL 2024

Zone 1 EOLIA : avancement global = 5%

– Terrassement = 80% • Maçonnerie = 0%

– Gros oeuvre = 5% • Second oeuvre = 0%

Zone 2 SOLIS : avancement global = 10%

– Terrassement = 95% • Maçonnerie = 0%
– Gros oeuvre = 10% • Second oeuvre = 5%

Zone 3 OASIS : avancement global = 53%

– Gros oeuvre = 99,99% • Second oeuvre = 30%

– Maçonnerie = 99,00%

Zone 4 LUMIA : avancement global = 38%

– Gros oeuvre = 80% • Second oeuvre = 10%

– Maçonnerie = 35%

Nos articles

CHANTIER AU 01 JUILLET 2024

Zone 1 EOLIA : avancement global = 10% – Terrassement = 80% • Gros oeuvre = 10% – Maçonnerie = 0% • Lots techniques =

CHANTIER AU 02 FEV 2024

Zone 3 OASIS : avancement global = 40% – Gros œuvre = 99,97% – Maçonnerie = 99,00% – Corps d’état secondaire = 12% Zone 4

plan 1

CHANTIER AU 02 NOVEMBRE 2023

Zone OASIS : Avancement global = 55,22% – Maçonnerie = 96,39% – Gros œuvre = 99,74 % – Corps d’état secondaire = 40,24%. Zone LUMIA