plan 1

CHANTIER AU 02 NOVEMBRE 2023

Zone OASIS : Avancement global = 55,22% – Maçonnerie = 96,39% – Gros œuvre = 99,74 % – Corps d’état secondaire = 40,24%. Zone LUMIA : Avancement global = 32,92% – Maçonnerie = 33,21% – Gros œuvre = 85,23% – Corps d’état secondaire = 13,88% Zone SOLIS : Avancement global = 3,41% – Gros œuvre = 6,52 % Zone EOLIA : Avancement global = 1,29%

Nos articles

CHANTIER AU 01 JUILLET 2024

Zone 1 EOLIA : avancement global = 10% – Terrassement = 80% • Gros oeuvre = 10% – Maçonnerie = 0% • Lots techniques =

CHANTIER AU 16 AVRIL 2024

Zone 1 EOLIA : avancement global = 5% – Terrassement = 80% • Maçonnerie = 0% – Gros oeuvre = 5% • Second oeuvre =

CHANTIER AU 02 FEV 2024

Zone 3 OASIS : avancement global = 40% – Gros œuvre = 99,97% – Maçonnerie = 99,00% – Corps d’état secondaire = 12% Zone 4