Actualite 1

CHANTIER 12 SEPTEMBRE 2023

Zone 3 OASIS : avancement global = 34,93%
– Gros œuvre = 99,97%
– Maçonnerie = 94,76%
– Corps d’état secondaire = 10,26%
 
Zone 4 LUMIA : avancement global = 14,06%
– Gros œuvre =  45,63%
– Maçonnerie = 3,29%
– Corps d’état secondaire = 3,64%

Nos articles

CHANTIER AU 01 JUILLET 2024

Zone 1 EOLIA : avancement global = 10% – Terrassement = 80% • Gros oeuvre = 10% – Maçonnerie = 0% • Lots techniques =

CHANTIER AU 16 AVRIL 2024

Zone 1 EOLIA : avancement global = 5% – Terrassement = 80% • Maçonnerie = 0% – Gros oeuvre = 5% • Second oeuvre =

CHANTIER AU 02 FEV 2024

Zone 3 OASIS : avancement global = 40% – Gros œuvre = 99,97% – Maçonnerie = 99,00% – Corps d’état secondaire = 12% Zone 4