Zone 3 OASIS : avancement global = 34,93%
– Gros œuvre = 99,97%
– Maçonnerie = 94,76%
– Corps d’état secondaire = 10,26%
Zone 4 LUMIA : avancement global = 14,06%
– Gros œuvre = 45,63%
– Maçonnerie = 3,29%
– Corps d’état secondaire = 3,64%
![](http://ivoire.work.gd/wp-content/uploads/2023/11/WhatsApp-Image-2023-01-13-at-17.28.10.jpeg)
![](http://ivoire.work.gd/wp-content/uploads/2023/11/abatta-vimllage-1024x576.jpg)
![](http://ivoire.work.gd/wp-content/uploads/2023/11/abatta-village-4-1024x576.jpg)
![](http://ivoire.work.gd/wp-content/uploads/2023/11/abatta-village-2-1024x576.jpg)
![](http://ivoire.work.gd/wp-content/uploads/2023/11/abatta-village-1024x576.jpg)
Zone 3 OASIS : avancement global = 34,93%
– Gros œuvre = 99,97%
– Maçonnerie = 94,76%
– Corps d’état secondaire = 10,26%
Zone 4 LUMIA : avancement global = 14,06%
– Gros œuvre = 45,63%
– Maçonnerie = 3,29%
– Corps d’état secondaire = 3,64%
Zone 1 EOLIA : avancement global = 10% – Terrassement = 80% • Gros oeuvre = 10% – Maçonnerie = 0% • Lots techniques =
Zone 1 EOLIA : avancement global = 5% – Terrassement = 80% • Maçonnerie = 0% – Gros oeuvre = 5% • Second oeuvre =
Zone 3 OASIS : avancement global = 40% – Gros œuvre = 99,97% – Maçonnerie = 99,00% – Corps d’état secondaire = 12% Zone 4