CHANTIER AU 01 JUILLET 2024

Zone 1 EOLIA : avancement global = 10% – Terrassement = 80% • Gros oeuvre = 10% – Maçonnerie = 0% • Lots techniques = 2% – Corps d’état secondaire = 0%   Zone 2 SOLIS : avancement global = 15% – Terrassement = 100% • Gros oeuvre = 15% – Maçonnerie = 1% • […]

CHANTIER AU 16 AVRIL 2024

Zone 1 EOLIA : avancement global = 5% – Terrassement = 80% • Maçonnerie = 0% – Gros oeuvre = 5% • Second oeuvre = 0% Zone 2 SOLIS : avancement global = 10% – Terrassement = 95% • Maçonnerie = 0%– Gros oeuvre = 10% • Second oeuvre = 5% Zone 3 OASIS : […]

CHANTIER AU 02 FEV 2024

Zone 3 OASIS : avancement global = 40% – Gros œuvre = 99,97% – Maçonnerie = 99,00% – Corps d’état secondaire = 12% Zone 4 LUMIA : avancement global = 18% – Gros œuvre =  48% – Maçonnerie = 5% – Corps d’état secondaire = 4%

CHANTIER AU 02 NOVEMBRE 2023

plan 1

Zone OASIS : Avancement global = 55,22% – Maçonnerie = 96,39% – Gros œuvre = 99,74 % – Corps d’état secondaire = 40,24%. Zone LUMIA : Avancement global = 32,92% – Maçonnerie = 33,21% – Gros œuvre = 85,23% – Corps d’état secondaire = 13,88% Zone SOLIS : Avancement global = 3,41% – Gros œuvre […]

CHANTIER 12 SEPTEMBRE 2023

Actualite 1

Zone 3 OASIS : avancement global = 34,93% – Gros œuvre = 99,97% – Maçonnerie = 94,76% – Corps d’état secondaire = 10,26%   Zone 4 LUMIA : avancement global = 14,06% – Gros œuvre =  45,63% – Maçonnerie = 3,29% – Corps d’état secondaire = 3,64%